Chahui Avenue in Nan’an to be open to traffic by the end of June

2025-04-17 00:25
听新闻
The construction site of Chahui Avenue in Nan’an on April 14
The construction site of Chahui Avenue in Nan’an on April 14

CHONGQING (CQNEWS) -- Currently, the first section of the Chahui Avenue project is approximately 95.5% complete. The main structure of the overpass of Yuma Road has been fully completed, with about 98.9% of its auxiliary works finished. The main structure of the Dongzhan Interchange has been fully completed, with approximately 95% of its deck’s auxiliary works finished. It is learned that Chahui Avenue is one of the key horizontal roads connecting Chongqingdong Railway Station, and it is expected to be completed and open to traffic by the end of June. (Photographed by Qi Lansen / Visual Chongqing) 

(Translated by Jane, Fathom Language Limited)